ROB-440 · Lesson 5 of 12 · 29 min

PLCs and IEC 61131-3 programming

In almost every robot cell, the robot is not in charge. A programmable logic controller (PLC) coordinates the cell: it reads sensors on conveyors and fixtures, tells machines and robots what to do and when, monitors guards through a safety controller, and talks to the operator panel and the plant's higher-level systems. Robot programmers who cannot read PLC code struggle to commission cells, and PLC programmers who do not understand robots write handshakes that deadlock. This lesson explains how PLCs work, introduces the IEC 61131-3 programming languages with short examples, and shows how a PLC and a robot exchange signals reliably. ROB-320 covered real-time systems in general; a PLC is a particular, very successful answer to the real-time problem for factory logic.

What a PLC is

The PLC was invented in 1968 and 1969 to replace the banks of relays that controlled automotive production lines. Changing relay logic meant rewiring cabinets; changing a PLC program meant editing software. The first programming language deliberately imitated relay wiring diagrams so that electricians could use it, which is why ladder logic still looks like a drawing of relay contacts and coils. Modern PLCs range from small units with a dozen inputs and outputs to large modular systems with thousands of points, redundant processors and integrated motion control. Major suppliers include Siemens, Rockwell Automation (Allen-Bradley), Schneider Electric, Mitsubishi Electric, Omron and Beckhoff, the last of which runs PLC software on industrial PCs.

PLCs are built for the factory: they tolerate electrical noise, vibration and temperature extremes; they run deterministic programs for years without rebooting; their input and output modules connect directly to 24 V DC sensors, solenoid valves, contactors and 4 to 20 mA analog instruments; and their programs can be monitored and modified while running. These properties, not raw computing power, are why PLCs remain dominant even though a laptop processor is far faster.

The scan cycle

A PLC executes its program in a repeating scan. At the start of each scan it reads all inputs into an input image table in memory. It then executes the user program from top to bottom using those stored values, writing results to an output image table. Finally it writes the output image to the physical outputs, performs communication and diagnostics, and starts again. Typical scan times are a few milliseconds to tens of milliseconds, depending on program size and processor.

Because inputs are read once per scan, the worst-case response time from an input change to an output change is about two scan times plus the input filter delay and the output switching delay. An input that changes just after it was read waits almost a full scan to be read, then a full scan to be processed and written. Short pulses can be missed entirely if they are shorter than one scan, which is why fast signals use interrupt inputs or high-speed counter modules.

\[t_{response,max} \approx t_{in} + 2\,t_{scan} + t_{out}\]

Worked problem

Will the PLC catch the pulse, and how fast does it respond?

A PLC has a 10 ms scan time, a 3 ms input filter and relay outputs with a 10 ms switching time. A part-present sensor on a fast conveyor produces 8 ms pulses. A reject solenoid must fire within 40 ms of a fault signal. Is the configuration adequate?

Show solution
  1. The 8 ms pulse is shorter than the 10 ms scan, so the PLC may miss it entirely; a high-speed counter or interrupt input is needed, or a longer pulse.
  2. Worst-case response for the reject: \( 3 + 2 \times 10 + 10 = 33 \) ms.
  3. 33 ms is under 40 ms, but with little margin; a transistor output switching in under 1 ms would bring the worst case to about 24 ms.

Answer: The pulse can be missed; use a fast input. The reject path meets 40 ms with relay outputs but is better with transistor outputs.

Inputs and outputs

Discrete inputs and outputs in North American and European factories are mostly 24 V DC. Sensors are either sourcing, called PNP, which switch the positive supply to the input, or sinking, called NPN, which switch the input to 0 V. The input module must match: a sinking input module expects a sourcing sensor, and vice versa. Mixing them up is one of the most common commissioning errors. Analog signals are usually 4 to 20 mA current loops, chosen because current is unaffected by wire resistance and because a reading of 0 mA reveals a broken wire, or 0 to 10 V for short runs. Increasingly, sensors and valve terminals connect through IO-Link or a fieldbus rather than individual wires, which Lesson 6 covers.

Worked problem

Scaling a 4 to 20 mA signal

A vacuum transmitter on a robot gripper outputs 4 mA at 0 kPa vacuum and 20 mA at 100 kPa vacuum. The PLC analog input converts 4 to 20 mA into raw counts from 0 to 27,648, a common convention on some PLC families. A reading of 15,200 counts arrives. What is the vacuum, and what current is that?

Show solution
  1. Fraction of span: \( 15\,200 / 27\,648 \approx 0.550 \).
  2. Vacuum: \( 0.550 \times 100 = 55.0 \) kPa.
  3. Current: \( 4 + 0.550 \times 16 \approx 12.8 \) mA.
  4. A reading corresponding to below about 3.6 mA would indicate a wiring fault rather than zero vacuum.

Answer: About 55 kPa vacuum, at roughly 12.8 mA.

IEC 61131-3 languages

IEC 61131-3 is the international standard for PLC programming languages. Its fourth edition, published in 2025, keeps four languages: two graphical, Ladder Diagram (LD) and Function Block Diagram (FBD), one textual, Structured Text (ST), and Sequential Function Chart (SFC) for organizing sequences. A fifth, the assembly-like Instruction List (IL), was deprecated in the third edition of 2013 and removed in the fourth. The standard also defines program organization units (programs, function blocks and functions), data types, and standard timers and counters. Vendors implement it with their own extensions, so programs are not fully portable between brands, but the concepts are shared, and the PLCopen organization publishes common function blocks for motion control and safety.

The IEC 61131-3 languages in the 2025 edition
LanguageStyleStrengthsTypical use
Ladder Diagram (LD)Graphical, relay-like rungsEasy for electricians to troubleshoot onlineDiscrete interlocks, simple machines, North American plants
Function Block Diagram (FBD)Graphical, blocks wired togetherClear signal flow, good for analog and controlProcess control, safety programs
Structured Text (ST)Textual, Pascal-likeCalculations, loops, data handling, state machinesComplex logic, recipes, communications
Sequential Function Chart (SFC)Graphical steps and transitionsVisualizes sequences and parallel branchesMachine sequences, batch processes

A ladder rung reads left to right: contacts in series form a logical AND, contacts in parallel form an OR, and a coil on the right is energized when a path of true contacts connects the left rail to it. The classic start-stop circuit uses a seal-in, or latching, contact so that a momentary start button keeps a motor running until stop is pressed.

A ladder diagram with two vertical rails. One rung has a normally open contact labeled Start in parallel with a normally open contact labeled Motor, then in series a normally closed contact labeled Stop and a normally open contact labeled Guard OK, ending at a coil labeled Motor.
A start-stop rung with a seal-in contact; the conveyor runs only while Stop is not pressed and the guard is closed
Structured Text for a seal-in, an on-delay timer and an up-counter; this is a listing, not run here
(* Same start-stop logic in Structured Text *)
ConveyorRun := (StartPB OR ConveyorRun) AND NOT StopPB AND GuardOK;

(* A TON on-delay timer: alarm if the part sensor stays blocked for 5 s *)
JamTimer(IN := PartSensor AND ConveyorRun, PT := T#5S);
JamAlarm := JamTimer.Q;

(* A CTU up-counter: count parts placed and flag a full pallet at 40 *)
PalletCount(CU := PartPlacedPulse, RESET := PalletRemoved, PV := 40);
PalletFull := PalletCount.Q;

Timers and counters are standard function blocks. TON, the on-delay timer, sets its output after its input has been true for a preset time; TOF, the off-delay timer, keeps its output on for a preset time after the input goes false; TP produces a fixed pulse. CTU and CTD count up and down. Edge detection blocks, R_TRIG and F_TRIG, produce a one-scan pulse when a signal rises or falls, which is essential for counting events rather than scans.

The seal-in drops out when the guard opens and needs a new start; the counter counts edges, not scans
# Simulating the seal-in rung and a rising-edge counter over a few scans
scans = [  # (StartPB, StopPB, GuardOK, PartSensor)
    (0, 0, 1, 0), (1, 0, 1, 0), (0, 0, 1, 1), (0, 0, 1, 1), (0, 0, 1, 0),
    (0, 0, 1, 1), (0, 0, 0, 1), (0, 0, 1, 0), (1, 0, 1, 0), (0, 1, 1, 0)]
run, prev_part, count = False, 0, 0
for i, (start, stop, guard, part) in enumerate(scans):
    run = (start or run) and not stop and guard          # seal-in rung
    rising = part and not prev_part                       # R_TRIG
    if rising and run:
        count += 1
    prev_part = part
    print(f"scan {i}: run={int(run)} part={part} rising={int(rising)} count={count}")
Output
scan 0: run=0 part=0 rising=0 count=0
scan 1: run=1 part=0 rising=0 count=0
scan 2: run=1 part=1 rising=1 count=1
scan 3: run=1 part=1 rising=0 count=1
scan 4: run=1 part=0 rising=0 count=1
scan 5: run=1 part=1 rising=1 count=2
scan 6: run=0 part=1 rising=0 count=2
scan 7: run=0 part=0 rising=0 count=2
scan 8: run=1 part=0 rising=0 count=2
scan 9: run=0 part=0 rising=0 count=2

Sequences and state machines

Robot cells are sequential: wait for a part, clamp it, tell the robot to load the machine, start the cycle, and so on. Sequences written as scattered ladder rungs become hard to follow and easy to break. Better practice is an explicit state machine, in SFC or in ST with a CASE statement on a step variable. Each step defines its outputs and the transition conditions to the next step, and fault and stop handling are explicit. Many companies have standard templates, often based on the PackML state model from the ISA-TR88.00.02 technical report, which defines states such as Idle, Starting, Execute, Holding, Held, Stopping, Aborting and Complete and the commands that move between them. A common state model across machines from different suppliers makes line integration and operator training much easier.

A cell sequence as a CASE state machine with time-outs and a fault step; this is a listing, not run here
CASE Step OF
  0:  (* idle: wait for part and robot ready *)
      IF PartAtFixture AND RobotReady AND AutoMode THEN Step := 10; END_IF
  10: ClampCmd := TRUE;
      IF ClampClosed THEN Step := 20;
      ELSIF StepTimer.Q THEN Fault := 101; Step := 900; END_IF
  20: RobotJob := 3; RobotStart := TRUE;          (* ask robot to run job 3 *)
      IF RobotBusy THEN RobotStart := FALSE; Step := 30; END_IF
  30: IF RobotJobDone THEN Step := 40;
      ELSIF RobotFault THEN Fault := 201; Step := 900; END_IF
  40: ClampCmd := FALSE;
      IF ClampOpen AND NOT RobotJobDone THEN Step := 0; END_IF
  900: (* fault: hold outputs safe, wait for operator reset *)
      RobotStart := FALSE;
      IF ResetPB THEN Fault := 0; Step := 0; END_IF
END_CASE

The robot-PLC handshake

The PLC and robot exchange a set of signals, either hard-wired or over a fieldbus. A typical interface has the PLC send a job or program number, a start request, and permission signals such as machine door open or fixture clamped; the robot returns ready, busy, job done, at home, and fault, plus position flags that tell the PLC when the robot is clear of a machine. The rules of the handshake must be written down and agreed by both programmers, ideally in an interface specification document.

A robust handshake is a closed loop: each request is held until acknowledged, and each acknowledgment is held until the request is removed. In the state machine above, the PLC holds Start until the robot reports Busy, then drops Start; it waits for JobDone, and does not start the next cycle until JobDone has dropped again. This four-phase pattern prevents a single signal glitch or a scan-time race from starting two cycles or skipping one. Every wait has a time-out leading to a fault with a specific number, so that operators and technicians know where the sequence stopped.

A typical robot-PLC interface
SignalDirectionMeaning
Job number (4 to 8 bits)PLC to robotWhich program or part variant to run
StartPLC to robotRequest to run the selected job; held until Busy
Machine clear to enterPLC to robotMachine door open and spindle stopped
Ready / In autoRobot to PLCRobot in automatic mode with no faults
BusyRobot to PLCJob accepted and running
Job doneRobot to PLCJob finished; held until Start is removed
Robot clear of machineRobot to PLCMachine may close its door and start
Fault codeRobot to PLCNumeric reason for a stop, shown on the HMI

Worked problem

Why the four-phase handshake matters

In a poorly written cell, the PLC sets Start for exactly one scan, and the robot polls its inputs every 12 ms. The PLC scan time is 5 ms. What can go wrong, and how does the four-phase handshake fix it?

Show solution
  1. A one-scan pulse lasts about 5 ms, shorter than the robot's 12 ms polling interval.
  2. The robot will miss the pulse in a large share of cycles, roughly \( 1 - 5/12 \approx 58 \) percent if timing is random, and the cell stalls.
  3. With a held request, Start stays on until the robot reports Busy, however long that takes.
  4. With a held acknowledgment, the PLC cannot mistake an old JobDone for a new one.

Answer: Short pulses between asynchronous controllers are missed; hold every request until acknowledged and every acknowledgment until the request drops.

HMIs, alarms and good PLC practice

The human-machine interface (HMI), a touch panel or PC screen, shows the cell's status, alarms and production counts and lets operators select modes, start and stop, and run recovery functions. Good alarm design follows the principle that every alarm should require an operator action and tell the operator what to do; the ISA-18.2 and IEC 62682 standards on alarm management describe how to avoid floods of meaningless messages. In a robot cell, the most useful HMI feature is often a clear display of which step the sequence is waiting at and which signal it is waiting for.

Good PLC practice includes consistent naming of tags, commented code, modular function blocks for repeated equipment such as clamps and conveyors, version control of programs, and a clear separation between standard control logic and safety logic. Safety functions, such as emergency stops, guard interlocks and light curtains, run in a safety-rated PLC or safety relay and are programmed under stricter rules, as Lesson 8 explains. A standard PLC can read safety status for display and sequencing, but must never be relied on to perform the safety function itself.

Common mistakes

  • MistakeSending one-scan pulses to a robot or another controller.

    InsteadUse held requests and acknowledgments in a four-phase handshake.

  • MistakeCounting scans instead of events.

    InsteadUse edge detection so that each part is counted once.

  • MistakeWiring sourcing sensors to sourcing input modules.

    InsteadMatch PNP sensors with sinking inputs and NPN sensors with sourcing inputs.

  • MistakeWriting sequences as scattered interlocked rungs.

    InsteadUse an explicit state machine with time-outs and a fault step.

  • MistakeImplementing emergency stops in standard PLC logic.

    InsteadUse safety-rated controllers for safety functions; standard PLCs only monitor them.

Summary and key terms

  • A PLC reads inputs, executes its program and writes outputs in a repeating deterministic scan.
  • Worst-case response is roughly input delay plus two scans plus output delay; short pulses need fast inputs.
  • 24 V DC discrete I/O must match sourcing and sinking types; 4 to 20 mA analog signals reveal broken wires.
  • IEC 61131-3:2025 defines LD, FBD, ST and SFC; Instruction List has been removed.
  • Timers, counters and edge detection are standard function blocks.
  • State machines, often following PackML, make sequences clear and recoverable.
  • Robot-PLC handshakes must hold requests until acknowledged, with time-outs and fault codes.
Programmable logic controller (PLC)
An industrial computer that executes control logic in a deterministic scan.
Scan cycle
The repeating sequence of reading inputs, executing logic and writing outputs.
Ladder Diagram
A graphical PLC language modeled on relay wiring.
Structured Text
A Pascal-like textual PLC language.
Seal-in contact
A contact that keeps a coil energized after a momentary start signal.
TON
An on-delay timer function block.
Edge detection
Producing a one-scan pulse when a signal changes state.
PackML
A standard state model for packaging and other machines.
Four-phase handshake
A request and acknowledgment pattern in which each signal is held until answered.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Scan 8 ms, input filter 2 ms, output 1 ms: worst-case response?

    Show answer

    \( 2 + 16 + 1 = 19 \) ms.

  2. A 4 to 20 mA level sensor reads 12 mA. What fraction of span?

    Show answer

    \( (12 - 4)/16 = 50 \) percent.

  3. Which IEC 61131-3 language was removed in 2025?

    Show answer

    Instruction List.

  4. Write a seal-in in words.

    Show answer

    Output on if (Start or Output) and not Stop.

  5. Why use R_TRIG for counting?

    Show answer

    So that a part held in front of a sensor for several scans is counted once.

  6. What does the PLC wait for before dropping Start?

    Show answer

    The robot's Busy acknowledgment.

  7. Why should every wait in a sequence have a time-out?

    Show answer

    So that a missing signal leads to a specific fault instead of a silent stall.

  8. Name three PackML states.

    Show answer

    Idle, Execute, Held, Stopping, Aborting, Complete and others.