Sign in or create a free account to continue.

PRIN-140 · Lesson 6 of 12 · 24 min

Directing a project I: the project board's role and decisions

Directing a project is the process through which the project board is accountable for the project's success. It starts when starting up sends the request to initiate and ends when the board authorizes project closure. Unlike the managing processes, it is not a sequence of activities carried out day to day. It is a set of decision points, plus continuous availability for advice and direction. This lesson looks at the board's role, the principle of management by exception that shapes it, and the five activities of directing. Lesson 7 looks at the authorization decisions in more depth.

The purpose of directing a project

In plain terms, directing a project lets the project board make the key decisions that only it can make, while delegating day-to-day management to the project manager. The board is accountable to the business layer for the project, and it exercises that accountability through a small number of formal decisions at defined points, through tolerances that set how much freedom the project manager has, and through the reports and escalations it receives. It does not attend daily stand-ups, approve every purchase or rewrite plans.

The objectives of directing can be summarized as follows. There is authority to initiate the project. There is authority to deliver the project's products. Management direction and control are provided throughout the project's life, and the project remains viable. Corporate, program or customer management has an interface to the project. There is authority to close the project. Plans for realizing the post-project benefits are managed and reviewed. Each of these objectives maps onto one or more of the activities described below.

A horizontal timeline spanning the project lifecycle with five labelled decision points above it. From left: authorize initiation, at the end of starting up; authorize the project, at the end of initiation; authorize a stage or exception plan, repeated at each stage boundary; authorize project closure, at the end of the final stage. Beneath the timeline, a continuous band labelled give ad hoc direction runs the full length. Arrows from below show the project manager's requests and reports feeding each decision point.
Directing a project: four authorizations at key points and continuous ad hoc direction.

The five activities

The five activities of directing a project (common PRINCE2 usage; summary in our own words).
ActivityTriggered byDecision or resultMain inputs
Authorize initiationRequest to initiate from starting upApprove, or not, the initiation stageProject brief; initiation stage plan
Authorize the projectRequest to deliver at the end of initiationApprove, or not, the project as defined in the PIDPID; benefits management approach
Authorize a stage or exception planEnd of a stage, or an exception planApprove the next stage plan, or an exception plan, or close prematurelyEnd stage report; next stage plan or exception plan
Give ad hoc directionReports, escalations, requests for advice, external eventsAdvice, decisions on escalated issues, instructionsHighlight reports; issue and exception reports; business layer advice
Authorize project closureClosure recommendation from closing a projectConfirm closure and notify the business layerEnd project report; lessons report; updated benefits management approach

Authorize the project and authorize a stage often happen at the same meeting at the end of initiation. The board approves the PID, which authorizes the project as a whole, and in the same meeting approves the stage plan for the first delivery stage. Some organizations record these as two decisions to keep the distinction clear: authorizing the project is a commitment to the whole investment in principle, but money is released stage by stage.

Management by exception

Management by exception is one of PRINCE2's principles and the key to how directing works. The board sets tolerances for each stage on the performance targets: time, cost, scope, quality, benefits, risk and, in PRINCE2 7, sustainability. As long as the project manager forecasts that the stage will finish within those tolerances, the board does not need to be involved in day-to-day decisions. When a forecast shows a tolerance will be exceeded, the project manager escalates through an exception report, and the board decides what to do. PRIN-131 studied tolerances and exceptions from the progress practice's side.

Management by exception makes the board's time valuable instead of wasted. A board that meets weekly to review every task trains its project manager to wait for instructions. A board that sets clear tolerances, reads concise highlight reports and responds promptly to exceptions trains its project manager to manage. The test of a well-directed project is not how often the board meets but how quickly it responds when it is needed.

Three board behaviours and what they mean for directing.
Board behaviourEffect on the projectDirecting in PRINCE2 terms
Weekly meetings to approve tasksProject manager waits for permission; decisions slowMicromanagement; not management by exception
No meetings and no responses to reportsExceptions sit unanswered; project driftsAbdication; directing not happening
Clear tolerances, short reports, decisions at stage boundaries, prompt responses to exceptionsProject manager manages; board decides what only it can decideManagement by exception working as intended

Board meetings and event-driven decisions

PRINCE2 does not require the board to hold regular progress meetings. The formal decisions happen at defined events: the request to initiate, the end of initiation, each stage boundary, an exception plan and closure. Between these, the board receives time-driven highlight reports and can respond to them without meeting. Many organizations still hold monthly board meetings, which is fine if they are used for direction rather than status reporting; if a meeting is spent reading out the highlight report, it adds nothing the report did not already provide.

Ridgeline Water's lessons log contained a lesson from a pipe renewal project whose board met only quarterly, so decisions waited up to 11 weeks. Its project management team design therefore includes monthly board meetings during delivery, decisions at stage boundaries scheduled in the plan, and an agreement that exception reports will be considered within five working days, by email if needed. The executive can make urgent decisions on the board's behalf, with the others informed.

The board's responsibilities in directing

Roles in directing a project.
RoleResponsibilities in directing (our summary)
ExecutiveChairs the board; owns the business case; makes the final decision when board members disagree; is accountable to the business layer
Senior userEnsures products will meet user needs; commits user resources; confirms user acceptance; is accountable for benefits being realized
Senior supplierEnsures products can be delivered; commits supplier resources; advises on technical feasibility and risk
Project assurance (board's delegate)Checks independently that the project is on track and that reports reflect reality
Business layer (outside the board)Sets project tolerances; receives escalations beyond them; receives closure notification

The board is not a democracy. Senior users and senior suppliers advise and commit resources, but the executive makes the decision, because the executive is accountable for the business case. In practice, a good executive seeks consensus, and a decision the senior user cannot support is a warning sign about benefits. But if the board cannot agree, the executive decides, and if the executive cannot decide within project tolerances, the matter goes to the business layer.

Reviewing the board's decision log

An assurance check sometimes looks at how a board has been directing: how long decisions took, whether exceptions were handled promptly and whether the board strayed into managing. The code below reviews an invented decision log from a previous project at the utility, the kind of evidence the lessons log drew on.

Reviewing an invented board decision log for delays and micromanagement.
from datetime import date
log = [
    ("Request to initiate", date(2022, 3, 1), date(2022, 3, 9), "authorize initiation"),
    ("PID and stage 2 plan", date(2022, 6, 1), date(2022, 8, 17), "authorize project and stage"),
    ("Exception report: contractor delay", date(2022, 10, 3), date(2022, 12, 19), "exception plan approved"),
    ("Highlight report: approve a 2,000 purchase", date(2022, 11, 2), date(2022, 11, 30), "approved"),
    ("End stage report and stage 3 plan", date(2023, 2, 1), date(2023, 3, 1), "authorize stage"),
    ("Closure recommendation", date(2023, 9, 4), date(2023, 9, 12), "authorize closure"),
]
waits = [(item, (decided - raised).days) for item, raised, decided, _ in log]
for item, days in waits:
    flag = "  <-- slow" if days > 21 else ""
    print(f"{item:44} {days:3d} days{flag}")
avg = sum(d for _, d in waits) / len(waits)
print(f"Average wait: {avg:.0f} days")
micro = [i for i, *_ in log if "purchase" in i]
print("Decisions the project manager should have made:", micro)
Output
Request to initiate                            8 days
PID and stage 2 plan                          77 days  <-- slow
Exception report: contractor delay            77 days  <-- slow
Highlight report: approve a 2,000 purchase    28 days  <-- slow
End stage report and stage 3 plan             28 days  <-- slow
Closure recommendation                         8 days
Average wait: 38 days
Decisions the project manager should have made: ['Highlight report: approve a 2,000 purchase']

Four of the six decisions waited more than three weeks, and the average wait was 38 days. The PID waited 77 days, so the project sat idle after initiation, and the exception report also waited 77 days, during which the project carried on as if nothing had happened. One decision, approving a small purchase, should never have reached the board at all; it was within the project manager's delegated authority. The lessons from this log shaped Ridgeline Water's board arrangements: decision dates planned in advance, a five-day response target for exceptions, and clear delegated limits so that small decisions stay with the project manager.

Directing and the business layer

The board is itself directed by the business layer. It must keep the business layer informed, typically through the executive, and it must refer anything beyond project tolerances upward. It also provides the business layer's interface to the project: if corporate strategy changes, or a program reprioritizes its projects, the business layer tells the board, which gives the project manager ad hoc direction. Ridgeline Water's executive reports to the general manager monthly and to council at each stage boundary, using the end stage report as the basis.

In a Canadian municipality, the business layer's oversight often includes council or a council committee receiving staff reports at key decisions. Aligning PRINCE2 stage boundaries with council meeting dates avoids a common delay: a stage ending two weeks after a council meeting may wait a month for the next one.

Worked problem

Is this a board decision?

During Ridgeline Water's pilot stage the project manager receives four requests: (a) the installation team wants to swap two streets in the schedule, with no effect on stage tolerances; (b) the supplier says meter prices will rise 12 %, which would breach the stage cost tolerance; (c) the senior user asks whether the portal should also show water-saving tips, a change costing 4 thousand; (d) council asks for a briefing on customer complaints. Which need the board?

Show solution
  1. (a) Swapping streets is within tolerance and within the project manager's authority: no board involvement.
  2. (b) A forecast breach of stage cost tolerance needs an exception report to the board.
  3. (c) A 4 thousand change is within the project manager's change authority limit of 10 thousand per change, if the change budget allows: the project manager can decide, and report it in the next highlight report.
  4. (d) A request from council comes from the business layer: the executive handles it, giving ad hoc direction to the project manager to prepare information.

Answer: Only (b) requires a board decision on an exception; (d) involves the executive as the link to the business layer; (a) and (c) stay with the project manager.

Common mistakes

  • MistakeHolding weekly board meetings to approve routine work.

    InsteadUse tolerances and management by exception; decide at defined points and on exceptions.

  • MistakeTreating the board as a voting committee.

    InsteadThe executive decides, advised by the senior user and senior supplier.

  • MistakeLetting exception reports wait for the next scheduled meeting.

    InsteadRespond promptly, by email or a special meeting if needed.

  • MistakeThinking directing starts when the project is authorized.

    InsteadDirecting starts with the request to initiate, at the end of starting up.

  • MistakeMaking decisions beyond project tolerances.

    InsteadRefer them to the business layer.

Summary and key terms

  • Directing a project lets the board be accountable through key decisions while delegating management.
  • It runs from the request to initiate until the board authorizes closure.
  • Its five activities are four authorizations and continuous ad hoc direction.
  • Management by exception, through tolerances, keeps the board out of day-to-day management.
  • Formal decisions are event-driven; regular meetings are optional and should add direction, not status reading.
  • The executive makes the final decision; the business layer handles anything beyond project tolerances.
Directing a project
The process through which the project board is accountable for the project.
Management by exception
Managing through tolerances so that higher levels are involved only when tolerances are forecast to be exceeded.
Authorize initiation
The board's decision to approve the initiation stage.
Authorize the project
The board's decision to approve the project as defined in the PID.
Ad hoc direction
Advice, decisions and instructions the board gives between formal authorizations.
Exception report
A report from the project manager to the board when a stage tolerance is forecast to be exceeded.
Event-driven control
A control that takes place when a specific event occurs, such as the end of a stage.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. When does directing a project start and end?

    Show answer

    It starts with the request to initiate and ends when the board authorizes project closure.

  2. Name the five activities of directing a project.

    Show answer

    Authorize initiation; authorize the project; authorize a stage or exception plan; give ad hoc direction; authorize project closure.

  3. Which principle explains why the board is not involved day to day?

    Show answer

    Manage by exception.

  4. Who makes the final decision if board members disagree?

    Show answer

    The executive.

  5. What does the board do with an issue beyond project tolerances?

    Show answer

    Refers it to the business layer.

  6. Does PRINCE2 require regular board meetings?

    Show answer

    No; decisions are event-driven, though meetings may be held.

  7. Which two decisions often happen at the end of initiation?

    Show answer

    Authorize the project and authorize the first delivery stage.

  8. What target did Ridgeline Water set for responding to exception reports?

    Show answer

    Within five working days.

  9. In the decision log, how long did the exception report wait?

    Show answer

    77 days.

  10. Who is the board's link to the business layer?

    Show answer

    Usually the executive.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz