CON-220 · Lesson 9 of 12 · 32 min

Delay, disruption and time extensions

Time is money in construction, for everyone. An owner whose building opens late loses rent or revenue and pays more interest. A contractor whose job runs long pays for supervision, site facilities, equipment and head office support for months it never priced, and may face liquidated damages. Subcontractors lose productivity when they cannot work in sequence. Delay claims are the largest and most complex construction claims, and they turn on the contract's time provisions, on notices given during the work and on the quality of the schedule. This lesson covers the legal framework: who bears delay, how time extensions are earned, liquidated damages, concurrent delay, acceleration and disruption. CON-210 covered schedule analysis; CON-420 covers delay claims in depth.

Types of delay

The law classifies delays by who is responsible and what remedy follows.

  • Excusable and compensable delay: caused by the owner or those it is responsible for, such as late drawings, late access, owner changes or suspension. The contractor gets more time and its delay costs.
  • Excusable but non-compensable delay: caused by events beyond either party's control, such as unusually severe weather, strikes not involving the contractor, or fire. The contractor gets more time but not money, and the owner cannot charge liquidated damages for that period.
  • Non-excusable delay: caused by the contractor or those it is responsible for, such as its subcontractors and suppliers. No time and no money; the contractor may owe liquidated or actual damages.

Only delays that affect the completion date, typically delays to activities on the critical path, entitle a contractor to a time extension. A delay to an activity with float may cost money through disruption but does not usually extend the contract time. This is why a good schedule, updated regularly, is the most important evidence in any delay dispute.

Matrix with three columns of delay types (excusable and compensable, excusable non-compensable, non-excusable) and rows for time extension, delay costs and liquidated damages.
Delay types and their consequences.

Contract provisions on delay

Under CCDC 2-2020 GC 6.5, if the contractor is delayed by an act or omission of the owner, the consultant or anyone employed by them, or by a stop work order from a court or public authority not caused by the contractor, the contract time is extended and the contractor is reimbursed its reasonable costs. If it is delayed by labour disputes, strikes, lock-outs, fire, unusual delay by common carriers or unavoidable casualties, or by causes beyond its control other than those, the time is extended but costs are not paid. The contractor must give notice of the delay within the period stated, and claims follow the GC 6.6 procedure. Supplementary conditions often add weather definitions and reduce the owner's liability for delay costs.

Delay events and typical results.
CauseCCDC 2-2020 resultNotes
Late owner drawings or decisionsTime and costsExcusable and compensable
Owner-directed changeTime and costs, via the changePrice time impact in the change
Strike not involving the contractorTime onlyExcusable, non-compensable
Abnormal weatherTime only if beyond the contractor's control and as definedNormal weather is the contractor's risk
Subcontractor lateNo time, no costsContractor responsible for its subcontractors
Supplier fire or unavoidable casualtyTime onlyCheck the definitions

Written notice: the condition that decides most delay claims

Nearly every contract requires written notice of a delay within a short period after the contractor becomes aware of it, followed by particulars and a claim. Courts have increasingly treated these notice requirements as conditions precedent: if notice is not given in time and in the required form, the claim fails, however meritorious.

Canadian courts generally enforce clear notice provisions. In several appellate decisions, contractors lost large delay claims because they did not give written notice within the contract's time, even though the owner knew about the delay from meeting minutes and correspondence. Courts sometimes accept that informal correspondence satisfied the clause if it contained the required information, or that an owner waived strict compliance, but these are fragile arguments. The safe course is formal written notice, in the form the contract requires, every time.

Worked problem

Writing an effective delay notice

A contractor learns on June 4 that structural steel shop drawings, already approved, must be revised because the architect changed a column grid. Fabrication will be delayed about three weeks. The contract requires written notice of any claim for time within 10 days. What should the notice contain and when should it be sent?

Show solution
  1. Send by June 14 at the latest, sooner if possible.
  2. Identify the event (architect's column grid change of June 4), the clause relied on, and that it will delay steel fabrication and erection.
  3. State that the contractor claims an extension of time and associated costs, with particulars to follow when the impact is known.
  4. Attach the instruction and the affected schedule activities, and send to the address and person named in the contract.

Answer: Send notice by June 14, identifying the event, the clause, the effect and the claim for time and costs.

Liquidated damages

Liquidated damages are a fixed sum per day or week, stated in the contract, that the contractor pays the owner for each day of non-excusable delay after the completion date. They spare the owner from proving its actual losses and give the contractor a known exposure. They also usually operate as the owner's exclusive remedy for delay.

Canadian courts enforce liquidated damages if they were a genuine pre-estimate of the owner's likely loss when the contract was made; a sum that is extravagant and unconscionable compared with any possible loss may be struck down as a penalty, leaving the owner to prove its actual damages. Courts are reluctant to intervene between sophisticated commercial parties.

Liquidated damages cannot be charged for excusable delay, and an owner who causes delay may lose the right to them. If the owner's delay makes the completion date impossible and no time extension mechanism applies, the contractor may argue that time is at large, meaning the contractor must complete within a reasonable time and liquidated damages fall away. Extension clauses exist partly to prevent this result.

Worked problem

Calculating liquidated damages

The completion date is September 30 and the contract sets liquidated damages of $4,500 per calendar day, capped at 5 % of the $6,000,000 contract price. Substantial completion is achieved on November 14. The contractor has been granted a 12-day extension for an owner change and proves a further 8 days of excusable delay for a strike. What liquidated damages apply?

Show solution
  1. Total delay: October has 31 days and November 14 more, so 45 days late against September 30.
  2. Excusable delay: 12 + 8 = 20 days.
  3. Non-excusable delay: 45 − 20 = 25 days.
  4. Damages: 25 × $4,500 = $112,500.
  5. Cap: 5 % × $6,000,000 = $300,000, not reached.

Answer: $112,500.

Concurrent delay

Concurrent delay occurs when two or more delays, one the owner's responsibility and one the contractor's, affect the critical path at the same time. Neither party can show that it alone caused the overall delay.

Canadian law is unsettled. Many contracts now address concurrency expressly. Without a clause, courts have used different approaches: granting the contractor time but no money for the concurrent period, so that neither side recovers delay damages from the other; apportioning responsibility between the parties; or requiring the claimant to separate the delays it caused from those it did not, failing which its claim may fail. Expert schedule analysis is almost always required.

Worked problem

Apportioning concurrent delay

During a 30-day period on the critical path, the owner's late design approvals and the contractor's late steel delivery each independently delayed completion. The contractor's daily time-related costs are $3,200; liquidated damages are $4,000 per day. Under the common approach of time without money for truly concurrent delay, what is the result for those 30 days?

Show solution
  1. The contractor receives a 30-day extension, so no liquidated damages: 30 × $4,000 = $120,000 avoided.
  2. The contractor recovers no delay costs: 30 × $3,200 = $96,000 not recovered.
  3. Each party bears its own costs for the concurrent period.

Answer: 30 days of time, no delay costs, no liquidated damages.

Acceleration and disruption

When a project falls behind, someone pays to catch up. Directed acceleration occurs when the owner orders the contractor to finish earlier than the contract requires, or to recover delay the owner caused; it is a change and is compensable. Constructive acceleration occurs when the contractor is entitled to an extension, asks for it, is refused, and is required to meet the original date, so it accelerates at its own cost to avoid liquidated damages. Courts recognize constructive acceleration claims where the contractor gave notice of the excusable delay, requested an extension, was refused and actually incurred acceleration costs.

Disruption is a loss of productivity, rather than a delay to completion: crews work out of sequence, trades stack in the same area, work is interrupted and restarted. Disruption is compensable when caused by the owner, but it is hard to prove. The preferred method is the measured mile: comparing productivity in an unaffected period or area with productivity in the disrupted period, on similar work, using the contractor's own records.

Worked problem

Measured mile

In an undisrupted period, a crew installed 2,400 units in 1,600 hours (1.5 units per hour). During owner-caused disruption, the crew installed 1,800 units in 1,500 hours. The loaded labour rate is $88 per hour. What is the lost productivity cost?

Show solution
  1. Hours that 1,800 units should have taken at the measured mile rate: 1,800 ÷ 1.5 = 1,200 hours.
  2. Actual hours: 1,500. Lost hours: 1,500 − 1,200 = 300.
  3. Cost: 300 × $88 = $26,400.

Answer: $26,400.

Head office overhead

Contractors also claim unabsorbed head office overhead for owner-caused delay: costs of the head office that would have been recovered from this project's revenue during the delay period. Several formulas exist. The Eichleay formula, developed by the US Armed Services Board of Contract Appeals in 1960 and used in federal contracting when the contractor was on standby and could not take other work, allocates overhead by the ratio of contract billings to total billings and divides by the days of performance.

\[\text{Daily overhead} = \frac{\dfrac{\text{Contract billings}}{\text{Total billings}} \times \text{Total overhead}}{\text{Days of performance}}\]

Canadian courts have accepted head office overhead claims using formulas such as Hudson, Emden and Eichleay, but they generally require proof that the contractor actually suffered the loss, for example because it could not take on other work during the delay.

Worked problem

Eichleay calculation

A contractor billed $9,000,000 on a contract over 360 days of performance, against total company billings of $45,000,000 in that period, with total head office overhead of $3,600,000. The owner caused a 40-day standby delay. What is the Eichleay claim?

Show solution
  1. Allocated overhead: ($9,000,000 ÷ $45,000,000) × $3,600,000 = $720,000.
  2. Daily rate: $720,000 ÷ 360 = $2,000 per day.
  3. Claim: 40 × $2,000 = $80,000.

Answer: $80,000.

Common mistakes

  • MistakeRelying on meeting minutes instead of formal delay notices.

    InsteadSend written notice in the form and time the contract requires for every delay event.

  • MistakeClaiming time for delays to activities with float.

    InsteadShow the effect on the critical path with schedule analysis.

  • MistakeAccelerating without first requesting a time extension.

    InsteadGive notice, request the extension and record any refusal before accelerating.

  • MistakeProving disruption with estimates instead of records.

    InsteadKeep daily labour and quantity records so a measured mile can be shown.

  • MistakeAssuming liquidated damages are always enforceable.

    InsteadThey may be unenforceable as a penalty, and cannot apply to excusable delay.

Summary and key terms

  • Delay is excusable and compensable, excusable but non-compensable, or non-excusable.
  • Only critical path delays extend the completion date.
  • CCDC 2-2020 GC 6.5 gives time and costs for owner delays and time only for neutral causes.
  • Delay notice requirements are often conditions precedent; give formal written notice every time.
  • Liquidated damages are enforceable if a genuine pre-estimate or reasonable forecast, and not a penalty.
  • Concurrent delay usually gives time without money unless apportioned.
  • Acceleration, disruption (measured mile) and head office overhead (Eichleay) are recoverable when caused by the owner and proved.
Excusable delay
A delay for which the contractor is entitled to more time.
Compensable delay
A delay for which the contractor is also entitled to costs.
Critical path
The longest chain of activities, which determines completion.
Liquidated damages
A fixed sum per period of delay agreed in the contract.
Penalty
An extravagant sum, unrelated to likely loss, that courts will not enforce.
Time at large
A situation where the completion date no longer binds and work must be done within a reasonable time.
Concurrent delay
Overlapping owner-caused and contractor-caused delays to completion.
Constructive acceleration
Acceleration forced by refusing an extension to which the contractor is entitled.
Measured mile
A comparison of productivity in unaffected and disrupted periods.
Eichleay formula
A formula for allocating unabsorbed head office overhead during owner-caused delay.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Name the three types of delay.

    Show answer

    Excusable and compensable, excusable non-compensable, non-excusable.

  2. Does a delay to an activity with 10 days of float extend completion?

    Show answer

    Not unless the delay exceeds the float.

  3. Completion was 18 days late; 6 days were excusable; LDs are $2,000 a day. What is owed?

    Show answer

    12 × $2,000 = $24,000.

  4. What makes liquidated damages a penalty?

    Show answer

    An extravagant amount unrelated to any genuine pre-estimate or reasonable forecast of loss.

  5. What is the usual result of truly concurrent delay?

    Show answer

    Time without money.

  6. What four elements support a constructive acceleration claim?

    Show answer

    Excusable delay, a request for extension, refusal, and actual acceleration costs.

  7. Normal productivity 2 units/h; disrupted 900 units in 600 h; $80/h. Loss?

    Show answer

    (600 − 450) × $80 = $12,000.

  8. Contract billings $5M of $25M total; overhead $2M; 250 days. Daily Eichleay rate?

    Show answer

    $400,000 ÷ 250 = $1,600.

  9. Why should notice be sent even if the owner already knows about a delay?

    Show answer

    Delay notice provisions are often conditions precedent.

  10. What is time at large?

    Show answer

    The completion date no longer binds, so work must be finished within a reasonable time.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz