Sign in or create a free account to continue.

PMP-131 · Lesson 1 of 12 · 29 min

Planning and managing quality

PMP-130 planned what Project Compass would deliver, when and for how much. This course covers the parts of the plan that decide whether those deliverables will be good enough, what could go wrong or unexpectedly right, what will be bought from others and how the whole plan is held together as things change: quality, risk, procurement and integration, ending with closing the project. This first lesson is about quality: what it means on a project, how to plan for it, what it costs to get right and to get wrong, and how quality management differs from inspection. The next lesson turns to the tools used to control quality and improve processes.

Where this course sits in the exam and the PMBOK Guide

At the time of writing (October 2026), the PMP exam follows the examination content outline that took effect on 9 July 2026, with three domains: People (about 33 % of scored questions), Process (about 41 %) and Business Environment (about 26 %). PMP-101 mapped the tasks. This course covers the Process tasks on quality, procurement and closure, finishes the integrated plan begun in PMP-130, and covers two tasks that the 2026 outline places in Business Environment: planning and managing risk, and managing and controlling changes. It also touches the task of removing impediments and managing issues, where issues meet risks.

Exam tasks covered in PMP-131. Governance, compliance and benefits are covered in PMP-150.
Task (paraphrased)Domain in the 2026 outlineWhere it is taught in this course
Plan and optimize quality of deliverablesProcessLessons 1 and 2
Plan and manage riskBusiness EnvironmentLessons 3 to 6
Plan and manage procurementProcessLessons 7 to 9
Develop an integrated plan and plan delivery (execution side)ProcessLesson 10
Manage and control changesBusiness EnvironmentLesson 11
Manage project closureProcessLesson 12
Remove impediments and manage issues (issue side)Business EnvironmentLesson 6

The PMBOK Guide, eighth edition, released digitally in late 2025, organizes guidance into seven performance domains (governance, scope, schedule, finance, stakeholders, resources and risk) and five focus areas (initiating, planning, executing, monitoring and controlling, and closing). Risk is a domain in its own right. Quality and procurement are not domain names in that structure; their guidance runs across domains, with quality closely tied to scope (requirements and acceptance) and governance, and procurement tied to resources, finance and governance. For the exam, the names of processes matter less than knowing what each activity is for, what it produces and which tool fits a given situation.

What quality means on a project

Quality is the degree to which a set of characteristics fulfils requirements. That definition sounds dry, but it has a sharp consequence: quality is judged against what was agreed, not against what the team thinks would be best. A kiosk that meets every requirement is a quality kiosk, even if a more expensive model exists. A beautiful app feature nobody asked for is not higher quality; it is unapproved scope, and PMP-130 called it gold plating.

Two related ideas are easy to confuse. Grade is a category assigned to deliverables with the same functional use but different technical characteristics: a basic kiosk and a premium kiosk with a larger screen and a coin acceptor are different grades. Low grade is not a problem if it is what the customer chose; low quality, meaning failure to meet the agreed requirements, always is. A low-grade, high-quality kiosk is simple and works reliably. A high-grade, low-quality kiosk has every feature and keeps freezing.

Quality vocabulary that exam questions rely on.
ConceptMeaningProject Compass example
QualityDegree to which characteristics meet requirementsKiosks complete 98 % of checkouts without staff help, as specified
GradeCategory of products with the same use but different featuresBasic self-checkout model chosen over a premium model with payment hardware
PrecisionRepeated measurements are close to one anotherThe read-rate test gives nearly the same result every time it is run
AccuracyA measured value is close to the true valueThe read-rate test result matches a manual count of tags actually read
ToleranceAcceptable range of resultsShelf heights within 10 mm of drawing dimensions
Control limitsBoundaries of normal process variation, calculated from dataTags encoded per hour stay within statistically calculated limits

Tolerances and control limits are another favourite distinction. A tolerance is set by the customer or the specification: it says what results are acceptable. Control limits are calculated from the process's own data: they say what variation is normal for the process as it currently runs. A process can be in control but produce results outside tolerance (it is stable but not capable), or be out of control while all results so far happen to be within tolerance (it is unpredictable). Lesson 2 shows control limits in action.

Principles of modern quality management

Project quality management draws on the work of quality pioneers such as Deming, Juran and Crosby, and on international standards such as the ISO 9000 family. Several principles appear repeatedly in exam questions.

Customer satisfaction comes first: understanding, evaluating, defining and managing requirements so that the customer's needs are met. Juran called this fitness for use. On Project Compass, the customers include the library board, branch staff and patrons, and their needs are captured in the requirements and acceptance criteria from PMP-130.

Prevention over inspection is the most important principle for exam purposes. Quality should be planned, designed and built in, not inspected in afterwards. Inspection finds defects that already exist; prevention stops them from occurring. The cost of preventing a mistake is generally much lower than the cost of finding and correcting it, and much lower again than the cost of a defect found by the customer. Crosby summed this up as "quality is free": the money spent on prevention is repaid by avoided failures.

Continuous improvement means that processes are measured and improved in cycles, such as Deming's plan-do-check-act, rather than fixed once. Management responsibility means that the people who control resources and processes are accountable for quality; Deming argued that most quality problems are caused by the system, not by individual workers. Finally, mutually beneficial partnerships with suppliers recognize that a project's quality depends heavily on what it buys, a theme that returns in the procurement lessons.

The quality management plan

In a predictive or hybrid project, the quality management plan is a component of the project management plan. It describes how quality requirements and standards will be identified and how the project will demonstrate compliance with them. It answers who is responsible for quality, which standards apply, which deliverables and processes will be reviewed, which quality control and assurance activities will be performed and when, which tools will be used, and how nonconformities and corrective actions will be handled. It should be proportionate: a small internal project may need a page; a regulated facility may need a detailed plan tied to a formal quality system.

Quality metrics translate requirements into measurable attributes and the way they will be measured. A metric needs a definition, a target and a measurement method; without the method, people will argue later about whether the target was met. Good metrics are few, relevant to what stakeholders care about and measurable at reasonable cost.

Quality metrics in the Project Compass quality management plan.
DeliverableMetricTargetHow measured
RFID taggingRead rate of tagged items at the security gates99.5 % or betterSample of 400 tagged items walked through gates weekly during tagging
Self-checkout kiosksUnassisted checkout success rate98 % of transactionsKiosk logs over a two-week soak test before opening
Mobile appCrash-free sessions99 % or betterApp store analytics for the first 30 days after release
Fit-outPunch-list items open at substantial completion25 or fewer, none safety-relatedJoint walk-through by architect, contractor and library
AccessibilityCompliance with the accessibility requirementsNo nonconformitiesIndependent accessibility review of drawings and of the finished space
TransitionStaff able to perform core kiosk tasks100 % of front-line staffObserved practical check after training

Some quality requirements come from law and standards, not from preference. For the Eastgate branch, the provincial building code's accessibility (barrier-free design) requirements apply to the fit-out, and the library has adopted CSA B651 as its design standard for accessible spaces and the Web Content Accessibility Guidelines (WCAG) 2.1 at level AA for its app. Requirements like these are non-negotiable: the quality management plan names them, assigns reviewers with the right competence and schedules reviews early, when correcting a problem is cheap.

The cost of quality

The cost of quality (COQ) is the total cost of all efforts related to quality over a product's life cycle. It has two halves. The cost of conformance is money spent to avoid failures: prevention costs, such as training, design reviews and better processes, and appraisal costs, such as testing, inspection and audits. The cost of nonconformance is money spent because of failures: internal failure costs found by the project, such as rework and scrap, and external failure costs found by the customer, such as warranty work, complaints and lost reputation. External failures are usually the most expensive and the most damaging, because they reach users and are hard to contain.

Planning estimates of the cost of quality for Project Compass, in thousands of dollars.
# Cost of quality for Project Compass ($000, invented planning estimates)
coq = {
    "Prevention": [("Accessibility design review", 12), ("Staff training on tag encoding", 9),
                   ("Kiosk vendor demo and pilot", 14)],
    "Appraisal": [("Tag read-rate testing", 22), ("Building inspections and walk-throughs", 15),
                  ("App test automation and device lab", 18)],
    "Internal failure": [("Re-encoding faulty tags", 16), ("Fixing punch-list items before opening", 24)],
    "External failure": [("Post-opening kiosk fixes and call-outs", 21), ("App fixes after release", 17),
                         ("Patron complaints and goodwill", 8)],
}
total = sum(v for items in coq.values() for _, v in items)
print(f"{'Category':18s}{'$000':>7s}{'Share':>8s}")
for cat, items in coq.items():
    s = sum(v for _, v in items)
    print(f"{cat:18s}{s:7d}{s / total:8.0%}")
conf = sum(v for c in ("Prevention", "Appraisal") for _, v in coq[c])
nonconf = total - conf
print(f"{'Total':18s}{total:7d}")
print(f"\nCost of conformance {conf}, cost of nonconformance {nonconf}")

# Option: add a second encoding station and pre-shipment tag audit (+11 prevention/appraisal)
# Expected effect from the pilot: re-encoding falls by half, kiosk call-outs fall by a third
new_conf = conf + 11
new_nonconf = nonconf - 16 / 2 - 21 / 3
print(f"With the extra prevention and appraisal: conformance {new_conf}, "
      f"nonconformance {new_nonconf:.0f}, total {new_conf + new_nonconf:.0f} (was {total})")
Output
Category             $000   Share
Prevention             35     20%
Appraisal              55     31%
Internal failure       40     23%
External failure       46     26%
Total                 176

Cost of conformance 90, cost of nonconformance 86
With the extra prevention and appraisal: conformance 101, nonconformance 71, total 172 (was 176)

The estimate shows almost as much expected spending on failure ($86,000) as on conformance ($90,000), and more than a quarter of the total on failures found after opening. The quality lead proposes adding a second pre-shipment audit of tag batches and moving the kiosk acceptance test earlier, for $11,000 more in prevention and appraisal. Pilot evidence suggests this would halve tag re-encoding and cut kiosk call-outs by a third. The model predicts a lower total cost of quality and, more importantly, fewer failures that patrons see in the first weeks of the branch's life. This is the economic argument behind prevention over inspection.

A bar chart of four cost of quality categories in thousands of dollars: prevention 35, appraisal 55, internal failure 40 and external failure 46. Labels above the bars group the first two as cost of conformance, 90, and the last two as cost of nonconformance, 86.
Cost of quality for Project Compass at the planning stage.

Cost of quality has limits. Some costs are hard to estimate, especially reputational damage, and spending on prevention shows diminishing returns: beyond some point, extra inspection costs more than the failures it prevents. Product life cycle matters too. A project that cuts quality costs to stay within budget may hand operations a product that is expensive to support. Life-cycle thinking, which PMP-130 introduced for cost estimating, applies equally to quality decisions.

Managing quality and controlling quality

Two activities are often confused. Managing quality, often called quality assurance, is about the processes: are we following the planned quality processes, and are they effective? It is executed throughout the project, typically through audits, process analysis and design for quality, and it builds stakeholder confidence that the deliverables will meet requirements. Controlling quality is about the products: do the deliverables meet the specified requirements? It involves measuring and testing outputs and comparing results with the metrics.

Managing quality versus controlling quality.
AspectManaging quality (assurance)Controlling quality
FocusProcessesDeliverables and outputs
QuestionAre we doing things the right way, and is it working?Is this output correct?
Typical activitiesQuality audits, process analysis, design reviews, checklists, root cause analysis of process failuresInspection, testing, measurement, statistical sampling, control charts
Main outputsQuality reports, test and evaluation documents, process improvements, change requestsVerified deliverables, quality control measurements, change requests
Compass exampleAudit of whether tag-encoding procedures are followed and records keptWeekly read-rate test of tagged items at the gates

A quality audit is a structured, independent review of whether project activities comply with organizational and project policies, processes and procedures. Audits identify good practices to share, gaps and shortcomings, and lessons that can improve the process on this and future projects. They are not punitive inspections of people; when they feel like that, people hide problems. On Project Compass, the library's facilities manager audits the contractor's own quality control records monthly, and the technology lead audits whether the app team's definition of done is actually applied to every story.

Two terms from PMP-130 connect here. Control quality produces verified deliverables: outputs that have been checked for correctness. Validate scope then obtains formal acceptance of those verified deliverables from the customer or sponsor. Order matters: you verify internally first, then ask the customer to accept. A deliverable that has not passed quality control should not be presented for acceptance.

Quality in adaptive and hybrid projects

Adaptive approaches build quality in through short feedback loops rather than relying on late inspection. Each user story has acceptance criteria. A team-wide definition of done lists the conditions every increment must meet, such as code reviewed, automated tests passing, accessibility checked and documentation updated. Practices such as test-driven development, continuous integration and frequent demonstrations catch defects close to where they are created. Retrospectives are a continuous improvement mechanism for the team's process. PMP-140 covers these practices in depth.

In a hybrid project like Project Compass, the quality management plan should say how quality is managed in each part and how the parts meet. The fit-out uses inspections, test reports and a formal punch list. The app team uses its definition of done and automated testing. Integration points, such as the app's connection to the library's catalogue system and the kiosks' connection to the same system, get joint test plans with clear owners, because defects at interfaces are the ones nobody feels responsible for.

Worked problem

Prevention or inspection?

During the pilot, 4 % of tags were mis-encoded because staff scanned the wrong barcode when two items lay close together on the encoding pad. The tagging supervisor proposes adding a second person to re-check every item. The quality lead suggests changing the procedure so that only one item is on the pad at a time, with a simple jig to hold it. Which approach better reflects modern quality management, and why?

Show solution
  1. Re-checking every item is inspection: it finds errors after they are made and roughly doubles labour for checking.
  2. The jig and one-item rule remove the cause of the error, so fewer defects are created in the first place. This is prevention.
  3. Prevention is usually cheaper over the volume of the job: re-checking 38,000 items costs far more than a jig and a revised procedure.
  4. Some appraisal remains appropriate: the weekly read-rate sample still confirms that the process works.

Answer: Change the process to prevent the error, keep a sampling check to confirm the result, and avoid 100 % inspection as the main control.

Common mistakes

  • MistakeTreating a premium product as higher quality.

    InsteadDistinguish grade (features) from quality (meeting requirements).

  • MistakeRelying on final inspection to achieve quality.

    InsteadPlan and build quality in; inspection confirms, prevention achieves.

  • MistakeConfusing tolerances with control limits.

    InsteadTolerances come from the specification; control limits come from process data.

  • MistakeCalling testing of deliverables quality assurance.

    InsteadTesting outputs is quality control; assurance focuses on processes, often through audits.

  • MistakePresenting deliverables for acceptance before they pass quality control.

    InsteadControl quality first, then validate scope with the customer.

Summary and key terms

  • Quality is the degree to which characteristics meet requirements; grade is a category of features.
  • Prevention over inspection, customer satisfaction, continuous improvement and management responsibility underpin quality management.
  • The quality management plan sets standards, responsibilities, activities and metrics; metrics need a target and a measurement method.
  • Cost of quality = conformance (prevention, appraisal) + nonconformance (internal, external failure). External failures cost most.
  • Managing quality focuses on processes and audits; controlling quality checks deliverables.
  • Verified deliverables from quality control go on to validate scope for acceptance.
  • Adaptive teams build quality in with acceptance criteria, a definition of done and fast feedback.
Quality
The degree to which a set of inherent characteristics fulfils requirements.
Grade
A category assigned to deliverables having the same functional use but different technical characteristics.
Cost of quality
All costs incurred over the life of a product to prevent nonconformance, appraise conformance and deal with failures.
Prevention cost
Cost of activities that stop defects from occurring, such as training and design reviews.
Appraisal cost
Cost of evaluating whether deliverables conform, such as testing and inspection.
Quality metric
A defined project or product attribute and how it will be measured.
Quality audit
A structured, independent review of whether project activities comply with policies and procedures.
Tolerance
The specified range of acceptable results.
Definition of done
A team checklist of criteria an increment must meet to be considered complete.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. A customer chose a basic kiosk model and it works flawlessly. Is this low quality?

    Show answer

    No. It is low grade and high quality.

  2. Name the two categories of cost of conformance.

    Show answer

    Prevention and appraisal.

  3. A defect found by patrons after opening is which type of cost?

    Show answer

    External failure cost.

  4. Which activity focuses on processes rather than deliverables?

    Show answer

    Managing quality (quality assurance).

  5. What must a quality metric include besides a target?

    Show answer

    A definition of how it will be measured.

  6. Which comes first: control quality or validate scope?

    Show answer

    Control quality.

  7. Who sets tolerances: the specification or the process data?

    Show answer

    The specification (the customer or requirements).

  8. Give one example of a prevention cost on Project Compass.

    Show answer

    Staff training on tag encoding, or the accessibility design review.

  9. What is the purpose of a quality audit?

    Show answer

    To check whether processes are followed and effective, and to find improvements.

  10. What adaptive artifact plays a role similar to a quality checklist for every increment?

    Show answer

    The definition of done.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz