PRIN-110 · Lesson 8 of 12 · 26 min

Tailor to suit the project

The seventh principle states that PRINCE2 is tailored to suit the project's context: its size, complexity, importance, risk, team capability, delivery approach and the organization around it. Tailoring is not a sign of doing PRINCE2 badly; it is a requirement of doing it well. A method applied identically to a two-week office move and a five-year infrastructure program would either crush the small project with bureaucracy or leave the large one dangerously under-managed. The tailoring principle makes sure the method fits, while the other six principles make sure that what remains is still PRINCE2.

What can and cannot be tailored

The rule is simple to state. The principles are not tailored away. Everything else can be adapted: the practices, the processes, the roles, the management products, the terminology and the techniques. Tailoring changes how the principles are applied, never whether they are applied.

Tailoring adapts everything except the principles themselves.
ElementCan be tailored?Examples
PrinciplesNo; how they are applied can be adaptedA brief stage boundary call still applies manage by stages
PracticesYesCombining risk and issue registers; a one-page business case
ProcessesYesCombining starting up and initiating on a simple project
RolesYes, within limitsExecutive also acting as senior user; project manager also team manager
Management productsYesHighlight reports as an email; product descriptions as a short table
TerminologyYesUsing the organization's word "gate" for stage boundary
TechniquesYesUsing Kanban for work packages; using the organization's risk scoring

Two levels of tailoring

Tailoring happens at two levels. At the organizational level, a company or government department adopts PRINCE2 and adapts it into its own project management method: its own templates, terminology, gating process and thresholds. This is sometimes called embedding. At the project level, each project then tailors the organization's method to its own context, deciding how many stages it needs, which management products to use and how formal reporting will be. Both levels should be documented. Project-level tailoring is recorded in the project initiation documentation, so the board and assurance can see what was decided and why.

Three stacked layers. The top layer is PRINCE2 guidance. The middle layer is the organization's method, adapted from PRINCE2 with its own templates, gates and terms. The bottom layer shows three projects, small, medium and large, each tailoring the organization's method differently. Arrows point downward between the layers.
PRINCE2 is first adapted into an organization's method, then tailored again for each project.

Factors that drive tailoring

The project context element of PRINCE2 7 lists many factors that influence tailoring. They can be grouped into a few questions.

  • Scale: how large is the budget, team and duration?
  • Complexity: how many interfaces, suppliers, technologies and stakeholders are involved?
  • Risk and importance: what happens if the project fails? Is it safety-critical or highly visible?
  • Delivery approach: is the work predictive, agile or a hybrid?
  • Capability: how experienced are the project manager, board and teams?
  • Organizational environment: what standards, gates, regulations and governance already apply?
  • Commercial context: are suppliers external, and under what contracts?
  • Sustainability and social context: what environmental and community expectations apply?

A tailoring decision matrix

Many organizations use a simple scoring matrix to suggest a tailoring level. Each factor is scored, the scores are weighted and the total points to a light, standard or full application of the method. The matrix does not replace judgment, but it makes tailoring decisions consistent and easier to explain to assurance.

Worked problem

Scoring a project for tailoring

An organization scores four factors from 1 (low) to 5 (high) with weights: budget size 30 %, risk 30 %, complexity 25 % and team inexperience 15 %. Scores of 2.0 or below suggest light tailoring, 2.1 to 3.5 standard and above 3.5 full. A project to replace meeting room booking software scores budget 2, risk 2, complexity 3 and team inexperience 1. Which level is suggested?

Show solution
  1. Budget: 2 × 0.30 = 0.60.
  2. Risk: 2 × 0.30 = 0.60.
  3. Complexity: 3 × 0.25 = 0.75.
  4. Team inexperience: 1 × 0.15 = 0.15.
  5. Weighted total: 0.60 + 0.60 + 0.75 + 0.15 = 2.10.

Answer: A score of 2.10 falls at the bottom of the standard band, so standard tailoring with some simplification is suggested. The project manager should explain any further lightening in the project initiation documentation.

Tailoring a small project

On a small, low-risk project, typical tailoring choices include:

  • one person acting as executive and senior user;
  • the project manager also acting as team manager;
  • starting up and initiating combined into a short activity producing a single project initiation document;
  • two management stages: initiation and one delivery stage;
  • highlight reports as short emails, perhaps fortnightly;
  • a combined register for risks, issues and lessons;
  • product descriptions as a short table rather than separate documents.

Every principle is still visible. The business case is short but reviewed at the end of initiation. Lessons are sought from the previous similar project. Roles are defined, even if combined. There are two stages with a decision point. Tolerances are set. Products are described. The tailoring is written down. That is a small PRINCE2 project done properly.

Tailoring a large or high-risk project

On a large or high-risk project, tailoring usually adds formality rather than removing it: more management stages, independent assurance reviews, more detailed product descriptions, a dedicated project support office, formal configuration management, and perhaps several team managers and a change authority. Large projects may also align stage boundaries with external gates, such as government investment approvals or regulatory milestones. The principle cuts both ways: it is as much a failure to under-manage a complex project as to over-manage a simple one.

PINO: PRINCE2 in name only

The opposite of good tailoring is sometimes called PINO, PRINCE2 in name only. A PINO project claims to use PRINCE2 but has removed or ignored one or more principles. Common signs include a business case that was never updated, a board that never meets, stage boundaries that are skipped, no tolerances, and templates filled in after the event to satisfy auditors. PINO projects often produce more paperwork than well-tailored ones, because documents are produced for compliance rather than use.

Legitimate tailoring keeps every principle; PINO quietly drops some.
Legitimate tailoringPINO
Business case shortened to two pages but reviewed at each stage endBusiness case written for approval and never looked at again
Executive and senior user combined, with assurance from another managerNo executive; decisions made informally by whoever is available
Two management stages with a brief boundary decisionOne stage; the board sees the project again at closure
Highlight reports by email with forecasts against toleranceNo tolerances; problems discovered at the end
Tailoring decisions recorded in the initiation documentationTemplates completed retrospectively for an audit

Tailoring and agile delivery

When delivery is agile, tailoring typically maps PRINCE2 concepts onto agile ones. Work packages may be defined as sets of backlog items for a release. Team managers may be product owners or delivery leads. Quality criteria may be expressed in a definition of done. Highlight reports may use burn-up charts. Scope becomes the main tolerance, with time and cost fixed. PRINCE2 Agile provides detailed guidance on this blend. Whatever the mapping, the principles still apply: the board still checks business justification at stage boundaries, which may align with releases, and still manages by exception.

Documenting tailoring

Tailoring decisions belong in the project initiation documentation, usually in a short section that lists each significant decision and the reason for it. This record matters for three reasons. It lets the board approve the way the project will be managed. It lets assurance check that tailoring has not removed a principle. And it lets a future project manager understand why the project was run as it was, which feeds learn from experience.

Worked problem

Recording tailoring decisions

Write three short tailoring records for a six-month internal process improvement project with a budget of 150,000.

Show solution
  1. Decision 1: combine executive and senior user (operations director). Reason: the director owns both the budget and the process; independent assurance from the finance manager.
  2. Decision 2: three management stages (initiation, design and pilot, rollout). Reason: the pilot result is a natural go or stop decision before rollout costs are committed.
  3. Decision 3: single combined register for risks, issues and lessons, reviewed fortnightly. Reason: small team; volume of entries expected to be low.

Answer: Each record names the decision, the reason and, where relevant, how the principle is still honored.

Tailoring the processes

Tailoring is not limited to documents. The seven processes can be adapted too. On a simple project, starting up and initiating a project can be combined into a short activity that produces a single initiation document. Controlling a stage and managing product delivery can be handled by the same person if the project manager is also the team manager. Managing a stage boundary can be a short meeting with a two-page end stage report. On a complex project, by contrast, each process may be supported by detailed procedures, a project office and formal approvals. What matters is that the purpose of each process is still achieved: the project is justified before significant resources are committed, it is planned before delivery starts, progress is controlled, boundaries are decision points and closure is orderly.

Tailoring terminology

Organizations often have their own vocabulary. They may call the executive the sponsor, the project board a steering committee, stage boundaries gates and the project initiation documentation a project charter. PRINCE2 allows terminology to be changed, as long as the meaning is preserved. The danger is that a renamed role quietly loses its responsibilities. A steering committee that only receives updates, rather than making decisions and holding tolerances, is not a project board in the PRINCE2 sense. When terminology is tailored, it is good practice to include a short mapping table in the tailoring record so that people trained in PRINCE2 can see how terms correspond.

A terminology mapping keeps meaning intact when names change.
PRINCE2 termCommon organizational termCheck
ExecutiveSponsorOwns the business case and is accountable
Project boardSteering committeeMakes decisions and sets stage tolerances
Stage boundaryGateIncludes a business case review and a go, change or stop decision
Project initiation documentationProject charterContains plans, controls and tailoring decisions
Exception reportEscalation noteTriggered by a forecast breach of tolerance

Reviewing tailoring as the project goes

Tailoring is not a one-off decision. As a project progresses, its context may change: the risk may grow, a new supplier may join, the team may become more experienced, or a program may take over some responsibilities. Stage boundaries are a good time to review whether the tailoring still fits. A project that started light may need more formality if problems emerge; a project that started heavy may simplify once processes are stable. Any change to tailoring should be recorded, with its reason, so that the board and assurance can see that every principle is still being applied.

Assurance reviewers often look at tailoring first, because it tells them where to expect evidence. If the tailoring record says highlight reports are monthly emails, the reviewer checks for those emails and for forecasts against tolerance in them. If it says the executive also acts as senior user, the reviewer checks that someone independent provides user assurance. Tailoring that is recorded clearly makes a project easier to review and easier to defend.

Common mistakes

  • MistakeTreating tailoring as permission to skip principles.

    InsteadTailor practices, processes and products; keep every principle.

  • MistakeApplying the full method identically to every project.

    InsteadScale the method to size, risk, complexity and context.

  • MistakeUnder-managing a complex, high-risk project in the name of tailoring.

    InsteadAdd formality and assurance where risk demands it.

  • MistakeMaking tailoring decisions informally and not recording them.

    InsteadRecord tailoring in the project initiation documentation.

  • MistakeFilling in templates afterwards to look compliant.

    InsteadUse management products as tools for decisions, not for audits.

Summary and key terms

  • PRINCE2 must be tailored to the project's context.
  • Principles are never tailored away; everything else can be adapted.
  • Tailoring happens at organizational and project levels.
  • Scale, complexity, risk, approach, capability and environment drive tailoring.
  • A weighted scoring matrix makes tailoring decisions consistent.
  • PINO projects claim PRINCE2 but drop principles.
  • Tailoring decisions and reasons belong in the project initiation documentation.
Tailoring
Adapting the method to suit the project's context.
Embedding
Adopting PRINCE2 into an organization's own project management method.
Project context
The internal and external setting that shapes how the method is applied.
PINO
PRINCE2 in name only: claiming to use PRINCE2 while ignoring principles.
Project initiation documentation
The documents that define how the project will be managed, including tailoring.
Gate
An organizational decision point, often aligned with a stage boundary.
Weighted scoring
Combining scores using weights to reflect relative importance.
PRINCE2 Agile
Guidance on combining PRINCE2 with agile delivery.
Definition of done
The agreed criteria for a backlog item to be considered complete.
Formality
The degree to which management products and controls are documented.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Can principles be tailored away?

    Show answer

    No; only how they are applied can be adapted.

  2. Name the two levels of tailoring.

    Show answer

    Organizational and project.

  3. Scores 4, 3, 3, 2 with weights 30, 30, 25, 15 %. Weighted total?

    Show answer

    1.2 + 0.9 + 0.75 + 0.3 = 3.15.

  4. Where are project tailoring decisions recorded?

    Show answer

    In the project initiation documentation.

  5. Give one sign of PINO.

    Show answer

    A business case never updated, skipped stage boundaries or no tolerances.

  6. Does tailoring always reduce formality?

    Show answer

    No; complex or risky projects may need more.

  7. Which role combination is common on small projects?

    Show answer

    Executive and senior user.

  8. In agile tailoring, which tolerance is often the main flexibility?

    Show answer

    Scope.

  9. What guidance covers PRINCE2 with agile in detail?

    Show answer

    PRINCE2 Agile.

  10. Why record the reason for each tailoring decision?

    Show answer

    So the board can approve it, assurance can check it and future projects can learn from it.