CON-130 · Lesson 11 of 12 · 34 min
Money maths: interest, cash flow, holdback and sales taxes
Construction is financed work. Contractors pay for labour, materials and equipment weeks or months before they are paid, owners borrow to fund projects, and payment rules hold back part of every invoice until the work is finished. The mathematics of money, interest, escalation, cash flow, retained amounts and sales taxes, therefore affects every project's profit as much as the mathematics of quantities. This lesson works through simple and compound interest, escalation of costs over time, the time value of money, progress payments with holdback or retainage, the cash flow gap that contractors must finance, and the sales taxes that apply to construction. It explains the arithmetic and the main rules; it is not legal, tax or accounting advice, and the rules change, so always confirm current requirements for a specific project.
Simple and compound interest
Interest is the price of borrowing money. Simple interest is calculated only on the original amount, the principal. Compound interest is calculated on the principal plus interest already earned or charged, so it grows faster. Construction loans, lines of credit and late-payment interest are usually compounded monthly or daily, while short-term calculations are often done with simple interest for convenience.
In the simple interest formula, P is the principal, r the annual rate and t the time in years. In the compound formula, F is the future amount, i the rate per compounding period and n the number of periods. An annual rate of 7.2 % compounded monthly has a monthly rate of 0.6 %. The effective annual rate, the true yearly cost after compounding, is (1 + i)ⁿ − 1 over one year, which for 0.6 % monthly is 1.006¹² − 1 = 7.44 %.
Worked problem
Interest on a construction loan
A contractor draws $250,000 on a line of credit at 7.2 % a year for 9 months. (a) What is the interest using simple interest? (b) What is it with monthly compounding? (c) What is the effective annual rate?
Show solution
- (a) Simple: I = 250,000 × 0.072 × (9 ÷ 12) = $13,500.
- (b) Compound: i = 0.072 ÷ 12 = 0.006 per month; F = 250,000 × 1.006⁹ = 250,000 × 1.05531 = $263,829; interest = $13,829.
- (c) Effective annual rate = 1.006¹² − 1 = 0.0744 = 7.44 %.
Answer: $13,500 simple; about $13,830 compounded monthly; effective rate 7.44 %.
Escalation
An estimate prepared today prices labour and materials at today's costs, but much of the work will be bought months or years later. Escalation is the expected increase in costs over that time, applied as a compound rate. Estimators usually escalate to the midpoint of construction, or to the expected purchase date of major items, because spending is spread across the construction period. Escalation rates come from cost indices, supplier forecasts and economic data, and can vary sharply by material and region.
Worked problem
Escalating an estimate to the midpoint of construction
A building is estimated at $4,200,000 in today's dollars. Construction starts in 12 months and lasts 12 months, so its midpoint is 18 months from now. Escalation is forecast at 4.5 % a year. (a) What is the escalated estimate? (b) How much is the escalation allowance? (c) If the forecast rose to 6 %, what would the allowance be?
Show solution
- (a) t = 1.5 years; factor = 1.045^1.5 = 1.0683; escalated estimate = 4,200,000 × 1.06825 = $4,486,670.
- (b) Allowance = 4,486,670 − 4,200,000 = $286,670.
- (c) Factor = 1.06^1.5 = 1.0913; allowance = 4,200,000 × 0.09134 = $383,600, about $97,000 more.
Answer: About $4.49 million escalated, an allowance of about $287,000 (about $384,000 at 6 %).
The time value of money
A dollar received later is worth less than a dollar today, because today's dollar could earn interest in the meantime. The present value of a future amount discounts it back to today at an interest rate, called the discount rate. Present value explains why holdback or retainage costs contractors money even when it is eventually paid in full, and why owners compare options with different payment timing using discounted values rather than raw totals.
Worked problem
The cost of waiting for retained money
A subcontractor has $100,000 retained on a project, to be released 14 months from now. The subcontractor's cost of borrowing is 8 % a year, compounded monthly. What is the present value of the retained amount, and what does the wait cost?
Show solution
- Monthly rate = 0.08 ÷ 12 = 0.006667; n = 14.
- PV = 100,000 ÷ 1.006667¹⁴ = 100,000 ÷ 1.0975 = $91,120.
- The wait costs about 100,000 − 91,120 = $8,880 in today's money, nearly 9 % of the retained amount.
Answer: The retained $100,000 is worth about $91,100 today; the wait costs about $8,900.
Progress payments
Most construction contracts pay monthly for work completed (Lesson 2). The contractor submits an application for payment showing the value of work done to date, often with materials stored on site, less previous payments and less a retained percentage. The owner or the owner's consultant certifies the amount, and the owner pays within the contract or statutory period. The contractor then pays its subcontractors their shares, and so on down the chain.
In Canada, the retained amount is called holdback. Provincial lien and prompt payment legislation requires owners to retain a statutory holdback, 10 % of the value of work in most provinces, to protect subcontractors and suppliers who may have lien rights. Ontario's Construction Act, for example, requires a 10 % holdback; since 1 January 2026 owners must also release accrued holdback annually on each anniversary of the contract (after publishing a notice), rather than only at substantial performance. Ontario's prompt payment rules require an owner to pay a proper invoice within 28 days unless it gives a notice of non-payment, and each payer down the chain to pay within 7 days of being paid. Alberta, Saskatchewan and several other provinces have adopted similar prompt payment regimes, and the federal Prompt Payment for Construction Work Act applies to federal construction projects. Details, deadlines and adjudication procedures differ, so check the current legislation for the province.
Worked problem
A progress payment with a retained amount
Using the schedule of values in Lesson 2, the work earned to date is $227,000 and previous payments certified totalled $140,000 before holdback. The contract is in Ontario, with a 10 % holdback and 13 % HST. (a) What is the value of work this period? (b) What is the holdback this period? (c) What amount is invoiced, including HST on the amount payable? (d) When must it be paid?
Show solution
- (a) Work this period = 227,000 − 140,000 = $87,000.
- (b) Holdback = 0.10 × 87,000 = $8,700. Total holdback to date = 0.10 × 227,000 = $22,700.
- (c) Payable before tax = 87,000 − 8,700 = $78,300; HST at 13 % = $10,179; invoice total = $88,479. GST/HST on the holdback generally becomes payable when the holdback itself is paid, so tax is calculated on the amount now payable.
- (d) Under Ontario's prompt payment rules, a proper invoice must be paid within 28 days unless the owner delivers a notice of non-payment within 14 days; the contractor then has 7 days to pay its subcontractors their shares.
Answer: Work this period $87,000; holdback $8,700; invoice $88,479 including HST; due in 28 days, with 7 days down the chain.
The cash flow gap
A contractor's costs are incurred as the work is done, but income arrives later: invoices are submitted at month end, certified, paid weeks later and reduced by the retained amount. The difference between cumulative costs and cumulative receipts is the contractor's negative cash position, which must be financed from working capital or borrowing. Plotting cumulative costs and cumulative receipts over time produces two S-shaped curves, with the gap between them showing the money the contractor has tied up in the project.
Worked problem
Financing the cash flow gap
A contractor incurs costs of $300,000 in each of months 1 to 3, bills cost plus a 10 % markup at the end of each month, and is paid 30 days after month end, less 10 % retainage. (a) What is the contractor's cash position at the end of month 3, just before the month-3 invoice is paid? (b) What is the approximate interest cost of carrying the gap for one month at 8 % a year?
Show solution
- Each monthly invoice = 300,000 × 1.10 = $330,000; payment received = 330,000 × 0.90 = $297,000.
- By the end of month 3: costs paid = 3 × 300,000 = $900,000. Payments received = invoices for months 1 and 2, received at the ends of months 2 and 3 = 2 × 297,000 = $594,000.
- (a) Cash position = 594,000 − 900,000 = −$306,000. The contractor is financing about $306,000.
- (b) Interest for one month ≈ 306,000 × 0.08 ÷ 12 = $2,040.
- Slow payment, high retainage and front-loaded costs all deepen the gap; that is why prompt payment laws, retainage limits and fair billing matter to contractors' finances.
Answer: About −$306,000 at the end of month 3, costing roughly $2,000 a month in interest.
Sales taxes on construction
In Canada, the federal Goods and Services Tax (GST) of 5 % applies to most construction services and materials, and in the participating provinces it is combined with the provincial portion as the Harmonized Sales Tax (HST): 13 % in Ontario, 15 % in New Brunswick, Newfoundland and Labrador and Prince Edward Island, and 14 % in Nova Scotia since April 2025. Registered businesses charge GST/HST on their invoices and recover the GST/HST they pay on inputs through input tax credits. British Columbia, Saskatchewan and Manitoba levy a separate provincial sales tax (PST), and contractors performing real property contracts are generally treated as the consumers of the materials they install, so they pay PST when buying materials and include it in their prices rather than charging it on the contract. Quebec levies the Quebec Sales Tax (QST) of 9.975 % alongside the GST. Rules for new housing rebates, self-assessment and specific materials are complex, so confirm treatment with current government guidance or an accountant.
Whatever the system, two arithmetic rules from Lesson 2 apply. Tax is calculated on the taxable amount, so check what the base includes. And to remove tax from a tax-inclusive total, divide by one plus the rate rather than subtracting the rate.
Worked problem
Sales tax in a material price
A contractor in Ontario receives a supplier invoice for $18,645 including 13 % HST. A contractor in British Columbia buys the same materials for $16,500 plus 5 % GST and 7 % PST. (a) What is the pre-tax amount of the Ontario invoice? (b) What will each contractor pay, and how much tax can each recover as an input tax credit if registered?
Show solution
- (a) Pre-tax = 18,645 ÷ 1.13 = $16,500; HST = $2,145.
- (b) Ontario: pays $18,645 and, if registered, claims the $2,145 HST as an input tax credit, so the net material cost is $16,500.
- British Columbia: pays 16,500 × (1 + 0.05 + 0.07) = $18,480. The GST of $825 is recoverable as an input tax credit; the PST of $1,155 is not, so the net material cost is $17,655, and the estimate must include the PST.
Answer: Ontario net cost $16,500 (HST recovered); British Columbia net cost $17,655 (PST is a real cost).
Putting it together
These calculations interact. Escalation raises the costs that are financed; slow payment and retained amounts lengthen the financing period; interest rates set its cost; and sales taxes change what materials really cost. A contractor deciding whether to bid a project with slow-paying owners or high retainage, or an owner deciding whether to release retained money early in exchange for a lower price, can compare options by putting each cash flow on a timeline and discounting it to a present value. Spreadsheets, covered in Lesson 12, make that comparison quick and transparent.
Common mistakes
MistakeUsing an annual rate as a monthly rate.
InsteadDivide the annual rate by 12 for monthly compounding, and use the number of months.
MistakeEscalating to the start of construction.
InsteadEscalate to the midpoint of spending or to purchase dates of major items.
MistakeTreating retained money as costless.
InsteadDiscount it: money received later is worth less, and the gap must be financed.
MistakeCalculating tax on a retained amount before it is payable.
InsteadFollow the tax rules for retained amounts; in Canada GST/HST on holdback is generally due when it is paid.
MistakeRemoving tax by subtracting the rate.
InsteadDivide a tax-inclusive total by (1 + rate).
Summary and key terms
- Simple interest is P r t; compound interest uses F = P (1 + i)ⁿ with rate and periods matched.
- Escalate estimates with (1 + e)ᵗ to the midpoint of construction.
- Present value PV = F ÷ (1 + i)ⁿ measures the cost of waiting for money.
- Progress payments deduct previous payments and a retained percentage.
- Holdback in Canada and retainage in the US are governed by contract and statute, with prompt payment rules.
- The gap between cumulative cost and receipts must be financed.
- Sales tax treatment differs by province or state and changes what materials really cost.
- Principal
- Amount borrowed or invested.
- Compound interest
- Interest calculated on principal plus accumulated interest.
- Effective annual rate
- True yearly rate after compounding.
- Escalation
- Expected increase in costs over time.
- Present value
- Value today of a future amount.
- Discount rate
- Rate used to convert future amounts to present value.
- Application for payment
- Monthly request showing work completed and amount due.
- Retained amount
- Percentage withheld from progress payments until completion.
- Prompt payment
- Legislation setting deadlines for construction payments.
- Input tax credit
- Recovery of GST/HST paid on business purchases.
Practice problems
Work each problem on paper first, then reveal the answer to check.
Simple interest on $80,000 at 6 % for 5 months?
Show answer
$2,000.
$80,000 at 0.5 % a month compounded for 5 months: interest?
Show answer
80,000 × (1.005⁵ − 1) = $2,020.
Effective annual rate of 0.75 % a month?
Show answer
1.0075¹² − 1 = 9.38 %.
Escalate $1.5 million at 3.5 % a year for 2 years.
Show answer
$1,606,838.
Present value of $50,000 due in 1 year at 6 % a year?
Show answer
$47,170.
Earned to date $640,000, previous payments $510,000 (before retention), 10 % retained. Net payable?
Show answer
$117,000.
Total retained to date on $640,000 at 10 %?
Show answer
$64,000.
Remove 13 % tax from $5,650.
Show answer
$5,000.
Remove 8.25 % tax from $2,165.
Show answer
$2,000.
Costs $200,000 a month; paid one month later at 90 % of a 10 % markup invoice. Cash position at the end of month 2, before the month-2 invoice is paid?
Show answer
−400,000 + 198,000 = −$202,000.
Lesson quiz · 5 questions