Sign in or create a free account to continue.

CON-340 · Lesson 11 of 12 · 25 min

Choosing a delivery method

By now it should be clear that no delivery method is best in general. Each is a bundle of trade-offs, and the right choice depends on what the owner is trying to achieve, what the project is like, what the market will offer, which risks the owner can manage, and what the owner's own team can do. This lesson brings those factors together into a structured selection process of the kind public owners now use, and looks at how risk allocation differs across methods, a topic CON-350 treats in more depth.

Start with the owner's goals

The first step is to state what success means for this project and rank the goals. Owners often say they want everything: lowest cost, fastest schedule, highest quality, least risk and full control. Forcing a ranking is uncomfortable but essential, because the methods trade these off against each other.

Owner goals and the methods that tend to serve or conflict with them.
GoalMethods that tend to serve itMethods that tend to conflict with it
Lowest initial price through competitionDesign-bid-build; low-bid design-buildProgressive models, IPD (negotiated price)
Earliest completionDesign-build, CMAR, IPDDesign-bid-build
Early price certaintyDesign-build lump sum, P3Agency CM, IPD (target only)
Owner control of designDesign-bid-build, agency CM, CMARDesign-build, P3
Single point of responsibilityDesign-build, P3Design-bid-build, agency CM
Managing high uncertainty and complexityCMAR, progressive design-build, IPD, allianceDesign-bid-build, lump-sum design-build
Life-cycle performanceDBFM or DBFOM P3Methods that end at handover
Minimizing owner staff effortDesign-build, P3 (after close)Agency CM, IPD

Then look at the project, the market and the owner

With goals ranked, the owner considers factors that can make a method unsuitable regardless of goals. Some are pass/fail: a method the owner lacks legal authority to use, a funding condition that rules a method out, or a market where no contractor will accept the risk. Others shift the balance.

Project, market and owner factors in method selection.
FactorQuestions to ask
Project complexityAre there difficult interfaces, existing facilities, phasing, novel systems or major unknowns?
Definition of scopeCan requirements be stated clearly now, or will they evolve?
Schedule pressureIs there a fixed deadline, such as an event, funding expiry or regulatory date?
Market conditionsHow many capable bidders exist? Will they accept fixed-price risk? Are trade markets thin?
Owner capacity and experienceDoes the owner have staff and advisers for this method? Has it used it before?
Legal and funding constraintsDoes the owner have authority? Do grant conditions restrict procurement?
Life-cycle prioritiesDoes the owner want the builder to maintain the asset long term?
Stakeholder and political factorsIs the project highly visible? Must the process be seen as maximally open?

Market sounding is valuable here. Before choosing, many public owners meet potential bidders, describe the project and the methods under consideration, and ask how the market would respond. If no general contractor will take fixed-price ground risk on a tunnel, a lump-sum design-build will attract few bids or very high ones. If local trades are fully booked, a construction manager may struggle to get competitive trade prices.

Comparing risk allocation

One way to compare methods is to list the project's main risks, estimate their expected cost, and ask who carries each under each method, and how efficiently. A risk transferred to a party that cannot control it is usually priced at a premium; a risk retained by the owner costs its expected value plus whatever the owner loses through poor management. The aim is not to transfer as much risk as possible, but to give each risk to the party best able to manage it at the lowest cost.

Heat map with risks as rows (design errors, construction cost, ground conditions, schedule, owner changes, integration, long-term performance) and delivery methods as columns, cells shaded by who carries the risk: owner, shared or builder side.
Who usually carries major risks under each delivery method (illustrative; contracts vary).
# Expected cost of retained and transferred risk for a $150 million hospital addition (illustrative, $ millions)
risks = {   # risk: expected cost if retained by the owner
    "Design errors and coordination": 6.0, "Construction cost on known scope": 5.0,
    "Ground conditions": 3.0, "Schedule delay": 4.5, "Systems integration": 3.5,
}
# share of each risk transferred to the builder side under each method, and premium charged on transferred risk
methods = {
    "Design-bid-build": ({"Design errors and coordination": 0.0, "Construction cost on known scope": 1.0,
                          "Ground conditions": 0.2, "Schedule delay": 0.5, "Systems integration": 0.3}, 0.30),
    "CM at risk":       ({"Design errors and coordination": 0.3, "Construction cost on known scope": 0.9,
                          "Ground conditions": 0.2, "Schedule delay": 0.5, "Systems integration": 0.5}, 0.25),
    "Design-build":     ({"Design errors and coordination": 1.0, "Construction cost on known scope": 1.0,
                          "Ground conditions": 0.5, "Schedule delay": 0.8, "Systems integration": 0.8}, 0.35),
    "IPD":              ({"Design errors and coordination": 0.5, "Construction cost on known scope": 0.5,
                          "Ground conditions": 0.5, "Schedule delay": 0.5, "Systems integration": 0.5}, 0.10),
}
for m, (transfer, premium) in methods.items():
    retained = sum(v * (1 - transfer[k]) for k, v in risks.items())
    priced = sum(v * transfer[k] for k, v in risks.items()) * (1 + premium)
    print(f"{m:17} retained {retained:5.1f}  transferred and priced {priced:5.1f}  total {retained + priced:5.1f}")
Output
Design-bid-build  retained  13.1  transferred and priced  11.6  total  24.7
CM at risk        retained  11.1  transferred and priced  13.6  total  24.7
Design-build      retained   3.1  transferred and priced  25.5  total  28.6
IPD               retained  11.0  transferred and priced  12.1  total  23.1

In this invented example the methods' total risk cost differs by a few million dollars, and the method that transfers the most risk is not the cheapest, because the market charges a premium for taking it. IPD looks cheapest here because the shared risk is assumed to be priced with a small premium, which is true only if the collaboration works. The numbers are only as good as the assumptions, but the exercise forces a useful discussion of which risks matter and who should hold them.

A weighted scoring matrix

Most structured selection tools combine pass/fail screens with a weighted scoring matrix. The owner chooses criteria from its goals and factors, weights them, and scores each candidate method against each criterion, usually in a workshop with its advisers. The Project Delivery Selection Matrix developed for transportation projects by the Colorado Department of Transportation and the University of Colorado, which the Federal Highway Administration has promoted, uses this approach, as do guides from the Design-Build Institute of America, the Construction Management Association of America and owners in both countries.

Flowchart: define and rank goals; apply pass/fail screens (legal authority, funding, market); shortlist methods; score shortlisted methods with weighted criteria and risk analysis; test sensitivity; select and document the decision.
A structured delivery method selection process.
# Weighted scoring of delivery methods with a sensitivity test (illustrative)
import random
random.seed(340)
criteria = {"Schedule": 0.25, "Cost certainty": 0.20, "Owner control": 0.15,
            "Complexity and risk management": 0.25, "Owner capacity fit": 0.15}
scores = {   # 1 (poor) to 5 (excellent) from a selection workshop
    "Design-bid-build": {"Schedule": 2, "Cost certainty": 4, "Owner control": 5, "Complexity and risk management": 2, "Owner capacity fit": 5},
    "CM at risk":       {"Schedule": 4, "Cost certainty": 3, "Owner control": 4, "Complexity and risk management": 4, "Owner capacity fit": 4},
    "Design-build":     {"Schedule": 5, "Cost certainty": 4, "Owner control": 2, "Complexity and risk management": 3, "Owner capacity fit": 3},
    "Progressive DB":   {"Schedule": 4, "Cost certainty": 3, "Owner control": 3, "Complexity and risk management": 5, "Owner capacity fit": 3},
}
def total(m, w):
    return sum(w[c] * scores[m][c] for c in w)
base = {m: total(m, criteria) for m in scores}
for m, t in sorted(base.items(), key=lambda kv: -kv[1]):
    print(f"{m:17} {t:.2f}")
# sensitivity: perturb each weight by up to +/-40 % and renormalize, 2,000 trials
wins = {m: 0 for m in scores}
for _ in range(2000):
    w = {c: v * random.uniform(0.6, 1.4) for c, v in criteria.items()}
    s = sum(w.values()); w = {c: v / s for c, v in w.items()}
    wins[max(scores, key=lambda m: total(m, w))] += 1
print("Share of trials each method ranks first:", {m: f"{n / 20:.0f} %" for m, n in wins.items()})
Output
CM at risk        3.80
Progressive DB    3.75
Design-build      3.55
Design-bid-build  3.30
Share of trials each method ranks first: {'Design-bid-build': '0 %', 'CM at risk': '73 %', 'Design-build': '2 %', 'Progressive DB': '25 %'}

The base scores put CM at risk first, narrowly ahead of progressive design-build. The sensitivity test shows how often each method stays first when the weights vary: if the leading method wins most trials, the choice is robust; if two methods trade places often, the owner should look harder at the criteria that separate them, or accept that either would be reasonable and decide on other grounds, such as market appetite or staff experience.

Worked problem

Changing one weight

Using the scores above, the owner decides that complexity and risk management should weigh 0.35 and schedule 0.15, keeping the other weights. Which method scores highest now?

Show solution
  1. Design-bid-build: 0.15×2 + 0.20×4 + 0.15×5 + 0.35×2 + 0.15×5 = 0.30 + 0.80 + 0.75 + 0.70 + 0.75 = 3.30.
  2. CM at risk: 0.15×4 + 0.20×3 + 0.15×4 + 0.35×4 + 0.15×4 = 0.60 + 0.60 + 0.60 + 1.40 + 0.60 = 3.80.
  3. Design-build: 0.15×5 + 0.20×4 + 0.15×2 + 0.35×3 + 0.15×3 = 0.75 + 0.80 + 0.30 + 1.05 + 0.45 = 3.35.
  4. Progressive DB: 0.15×4 + 0.20×3 + 0.15×3 + 0.35×5 + 0.15×3 = 0.60 + 0.60 + 0.45 + 1.75 + 0.45 = 3.85.

Answer: Progressive design-build now edges ahead, 3.85 against 3.80. When results are this close, the matrix has done its job by narrowing the choice; the final decision should rest on the factors the matrix cannot capture well.

Common patterns

Although every project is different, experience suggests some common matches between project types and methods.

Common project types and the methods often chosen for them.
Project typeMethods often chosenWhy
Simple, well-defined public buildingsDesign-bid-build, design-buildClear scope, competitive market, price competition valued
Complex institutional buildings and occupied renovationsCMAR, agency CM, IPDBuilder input, phasing, owner control
Highways and bridges with clear performance requirementsDesign-build, CM/GC for complex sitesSpeed and innovation; CM/GC where risks are uncertain
Water and wastewater plantsProgressive design-build, CMAR, design-buildProcess complexity, operations during construction
Large hospitals with long-term maintenanceDBFM P3, progressive P3, allianceLife-cycle accountability, large scale
Major transit lines and tunnelsAlliance, progressive models, packaged design-buildIntegration and ground risk too large for fixed price
Private commercial and industrialNegotiated design-build, CMARSpeed, relationships, private freedom to negotiate

Documenting and revisiting the decision

Public owners should record the selection process: goals and weights, screens applied, methods considered, scores, risk analysis, market feedback and the final rationale. The record supports approvals, audits and lessons learned. It also helps if circumstances change. A method chosen in a competitive market may need revisiting if the market tightens; a design-build chosen for speed may need reconsidering if a funding delay removes the schedule pressure. Revisiting a decision before procurement starts is cheap; changing method after a procurement fails is expensive.

After completion, owners that compare outcomes, including cost growth, schedule growth, quality, claims and stakeholder satisfaction, against the reasons a method was chosen build an evidence base for future decisions. Many large public owners now publish such reviews.

Hybrid and packaged approaches

Large programs do not have to use one method for everything. Owners often package a project into several contracts with different methods: early works by design-bid-build, a main building by CM at risk, a central plant by design-build with a performance guarantee, and equipment by owner pre-purchase. Transit agencies commonly split civil works, stations, systems and vehicles into separate packages with different methods. Packaging lets each part use the method that suits its risks, but it creates interfaces between contracts, and someone, usually the owner or its program manager, must manage them. A packaging decision should therefore be scored like a delivery method, with interface risk counted explicitly.

Common mistakes

  • MistakeStarting from a preferred method and justifying it afterwards.

    InsteadRank goals and apply screens before scoring methods.

  • MistakeTransferring as much risk as possible.

    InsteadAllocate each risk to the party best able to manage it at the lowest cost.

  • MistakeIgnoring the market.

    InsteadSound the market on capacity and risk appetite before choosing.

  • MistakeTreating a close score as a clear answer.

    InsteadTest sensitivity and decide close calls on factors the matrix cannot capture.

  • MistakeNever revisiting the decision.

    InsteadRevisit if the market, funding or schedule pressure changes before procurement.

Summary and key terms

  • Method selection starts with a ranked statement of the owner's goals.
  • Pass/fail screens remove methods that are not legally, financially or practically available.
  • Project complexity, scope definition, schedule pressure, market conditions and owner capacity shift the balance among methods.
  • Risk should go to the party best able to manage it; transferring risk costs a premium.
  • Weighted scoring matrices, with sensitivity tests, structure the comparison.
  • Common patterns match methods to project types, but each project needs its own analysis.
  • Owners should document the decision, revisit it if conditions change, and review outcomes afterwards.
Selection criteria
The factors used to compare delivery methods.
Pass/fail screen
A test that eliminates methods not available or suitable regardless of score.
Market sounding
Early consultation with potential bidders about a project and its delivery.
Risk premium
The amount a party adds to its price for taking a risk.
Weighted scoring matrix
A table scoring options against weighted criteria.
Sensitivity analysis
Testing how results change when assumptions or weights vary.
Project Delivery Selection Matrix
A structured selection tool developed for transportation projects in Colorado and promoted by FHWA.
Risk allocation
The assignment of risks to the parties under a contract.
Owner capacity
The owner's skills and staff to manage a delivery method.
Lessons learned
Documented experience used to improve future decisions.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why must the owner rank its goals?

    Show answer

    Because methods trade goals off against each other.

  2. Name two pass/fail screens.

    Show answer

    Legal authority, funding conditions, market willingness to take the risk.

  3. What is market sounding?

    Show answer

    Consulting potential bidders before choosing a method and procurement approach.

  4. Why is transferring the most risk not always cheapest?

    Show answer

    Parties charge a premium for risks they take, especially risks they cannot control.

  5. A method scores 4, 3, 5 on criteria weighted 0.5, 0.3, 0.2. What is its weighted score?

    Show answer

    2.0 + 0.9 + 1.0 = 3.9.

  6. What does a sensitivity test on weights show?

    Show answer

    How robust the ranking is when weights change.

  7. Which methods suit complex occupied renovations?

    Show answer

    CMAR, agency CM or IPD.

  8. Which methods suit major transit lines with large integration and ground risks?

    Show answer

    Alliance or progressive models, or carefully packaged design-build.

  9. Why document the selection decision?

    Show answer

    For approvals, audits, lessons learned and revisiting if conditions change.

  10. When is changing the delivery method least costly?

    Show answer

    Before procurement starts.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz